Hi,

Here i am implementing activity based costing.here ps module is there.I created network activity in project level, i assigned workcenter, work hours and activity type in network activity level.But i am not getting any project plan and actual cost for project level in s_alr_87013543 t.code.My client wants to calculate the project cost.In production level i am capturing the plan and actual cost,But in project level i am not getting the any cost.Any body please help me.

Thanks & Regards,

Reddy

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member9084
Participant
0 Kudos

Hi,

If internal activity cost is not getting calculated check following cost calculatation log:

probable reason could be:

-Activity price not maintained on the cost center of work center

-Activity hours are not maintained in project

- Control key config should allow costing.

-Activity type master data are not correctly maintained.

Rajesh

Edited by: CA Rajesh Porwal on Apr 25, 2011 1:09 PM

Former Member
0 Kudos

The above steps i already maintained,But i am not getting the internal cost.Please help me.Please tel me the activity assignments in project level.

Regards

Reddy

Former Member
0 Kudos

Hi,

1. Attach valuated material to activity and save to get planned cost

2. For actual need to do procurement cycle for the material attached.

Best regards,

Former Member
0 Kudos

With material i am getting the plan cost, without material i am not getting the any cost. design is my network header, there is no any material of design.In this network i am not getting the plan cost.please help me

Reddy

Former Member
0 Kudos

This is completely internal activity cost caluclation.Here i am not given the material.How we can capture the internal cost in project level.

Design is my network header.there is no any material for design.How we can capture the design plan cost.

Regards

Reddy

Former Member
0 Kudos

This is completely internal activity cost caluclation.Here i am not given the material.How we can capture the internal cost in project level.

Design is my network header.there is no any material for design.How we can capture the design plan cost.

Regards

Reddy