Hi,
Here i am implementing activity based costing.here ps module is there.I created network activity in project level, i assigned workcenter, work hours and activity type in network activity level.But i am not getting any project plan and actual cost for project level in s_alr_87013543 t.code.My client wants to calculate the project cost.In production level i am capturing the plan and actual cost,But in project level i am not getting the any cost.Any body please help me.
Thanks & Regards,
Reddy
Hi,
If internal activity cost is not getting calculated check following cost calculatation log:
probable reason could be:
-Activity price not maintained on the cost center of work center
-Activity hours are not maintained in project
- Control key config should allow costing.
-Activity type master data are not correctly maintained.
Rajesh
Edited by: CA Rajesh Porwal on Apr 25, 2011 1:09 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
1. Attach valuated material to activity and save to get planned cost
2. For actual need to do procurement cycle for the material attached.
Best regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
105 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.