how to change cost of labour hour in workcenter.

Former Member
0 Kudos

Hiii Experts,

Please help me out.. how to change the cost of labour hour in a work center....

Thanks & Regards,

sampath

Edited by: sampath s on Apr 24, 2011 12:53 PM

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi ,

Please Check in KP27,by entering the controlling area, also included the version and the period say 01 to 01 or else 01 to 02 and enter * in the cost center and the activity type name say LABOUR and click on overview screen F5.

the purpose is to find the assigned rates.

This is important because the rate will determine the cost calculation from work center.

You can select the arrow for forward key to check for next cost center and activity type combination.

After what you did , please check with this report as below :

S_ALR_87013611 - Enter the following Controlling Area, Fiscal Year , period and version.

S_ALR_87013646 - check for the activty type and period combination and S_ALR_87013617 for Activity type:ranges.

Also Please use of others CO related reports,

S_ALR_87013857 Range: Activity Types

S_ALR_87013879 Activity Types: Period Breakdown

S_ALR_87013880 Activity Types: Scheduled/Plan

S_ALR_87015032 Range: Activity Types

Hope can help.

TQ.

Former Member
0 Kudos

Hi Experts,,

Thanks for the valuable inputs... before i close this if i change the cost of labour hour here whether it will affect the rate of Cost center and the activity type...... and also please help me whether it will affect the Worcenter's since the same Cost center assigned to 5 Work center...

Kindly help me out.. it will be very helpful for me..

Thanks & regards,

Sampath

Former Member
0 Kudos

Hi Sampath,

Surely if you change labour hour rate in KP26 it will affect cost booking in respective cost center. If you are going to use same cost center in different work centers & also same case for Labour Hour activity type then better discuss with CO consultant. Also KP26 is maintained by CO consultant. So better you make these changes in coordination with your CO consultant and then proceed.

Regards,

Tejas

Former Member
0 Kudos

Thanks for your support......

Regards,

sampath

Answers (1)

Answers (1)

sundaresan_velayudam
Active Contributor
0 Kudos

In Kp26 enter the version 0 from period as 1 and to period as 12 and fiscal year as 2011

enter the cost center mentioned in work center in cost center field and labor activity type in activity type field and enter

and change the value and save