how to change cost of labour hour in workcenter.

Hiii Experts,

Please help me out.. how to change the cost of labour hour in a work center....

Thanks & Regards,

sampath

Edited by: sampath s on Apr 24, 2011 12:53 PM

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Apr 24, 2011 at 11:44 AM

    Hi ,

    Please Check in KP27,by entering the controlling area, also included the version and the period say 01 to 01 or else 01 to 02 and enter * in the cost center and the activity type name say LABOUR and click on overview screen F5.

    the purpose is to find the assigned rates.

    This is important because the rate will determine the cost calculation from work center.

    You can select the arrow for forward key to check for next cost center and activity type combination.

    After what you did , please check with this report as below :

    S_ALR_87013611 - Enter the following Controlling Area, Fiscal Year , period and version.

    S_ALR_87013646 - check for the activty type and period combination and S_ALR_87013617 for Activity type:ranges.

    Also Please use of others CO related reports,

    S_ALR_87013857 Range: Activity Types

    S_ALR_87013879 Activity Types: Period Breakdown

    S_ALR_87013880 Activity Types: Scheduled/Plan

    S_ALR_87015032 Range: Activity Types

    Hope can help.

    TQ.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Apr 24, 2011 at 11:03 AM

    In Kp26 enter the version 0 from period as 1 and to period as 12 and fiscal year as 2011

    enter the cost center mentioned in work center in cost center field and labor activity type in activity type field and enter

    and change the value and save

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.