While planing activity independent primary and secondary costs, distribution key is required probably in order to distribute the annual costs to the posting periods. Is this logic correct?

And if this is so, then in variable activity dependent costs, distribution key should not be required because variable activity dependednt cost will be directly proporstinal to the output activity of the cost centre. But in KP06 (as per the CO manualTFIN20-2 MA I), distribution key is also given in case of such costs? Why? I understand that those variable activity dependednt costs should not be divided in posting periods equally but on the basis of activity output in each posting period. Then why distribution key is required?

Please help clarify my concepts

Asif, Karachi Pakistan

Accepted Solutions (0)

Answers (1)

Answers (1)

ajaycwa1981
Active Contributor
0 Kudos

Hi Asif bhaijaan

Greetings from India!

Dist Key is always required whether you Plan Act Dep or Indepn costs..

The purpose of Dist Key is to distribute the Annual values across the 12 periods.... So, this is required in both cases....

During the Act Dependant planning, there is no link in the system which says X should be the Plan Cost for Y Output.... Hence, a dist key is required to distribute plan costs across periods

br, Ajay M