Need Project costing details

Dear All,

Hi, I created one new project in project systems and i created wbs element, network and network activity.In network activity i maintained the work center, work hours and activity type.Here i am implementing activity based costing.But i am getting the any project cost in s_alr_87013543 t.code.In order level i am getting all the internal cost,but in project level i am not getting any internal activity cost.Anybody please help me.

Regards

Reddy

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • author's profile photo
    Former Member
    Posted on May 04, 2011 at 01:26 PM

    Hi

    As Per My Understanding , For Activity variance you need to maintain the Planned Price in KP26 For the Work Centers, so please check if that are maintained. Correct me if Iam worng.

    Thanks

    Goutam