Dear Experts,

I want linkage between BPO and its WBS.I got closer maps lik CKIS & CKBS.

I am making a Z report which shows Planned material vs Actual material assigned to particular WBS.

Regards

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

The following is valid if you are selecting the category "B" in the Unit costing of your WBSE.

(There is another way to copy item details from BPO while creating unit cost estimate for your WBSE. This will not store the BPO number anywhere).

- Get "Object Number (PRPS_OBJNR)" of your WBSE from PRPS.

- Pass this into table BPGE & get the "Cost Estimate number (BPGE_KALNR)"

- Pass this into CKIS & get the corresponding BPO Number "CKIS_EXTNR"