Use ot alternate BOM

Former Member
0 Kudos

Hi

We have alternate BOM of a GF material, How can i use boththe BOMS in MRP run, and If we run MRP 2 time for the same material Ist time i use BOM no 1 and in IInd run change the BOM and run the MRP what will be the impact on my PR`s

Thanks

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Dear Sir,

Other way of doing is that make one production version active and then run MRP and then the other.Go to C223 and make inactive or make it inactive through MRP-4.Avinash Sir, please be free to call

Regards

Bhupendra Singh

Edited by: laxmi23101975 on Jun 15, 2011 12:28 PM

Former Member
0 Kudos

thanks

dhaval_choksi3
Active Contributor
0 Kudos

Use Quata Arrangment, t.code is MEQ1. You have to create 2 production version with different alternate bom. and give %quata to this production version.

Regards,

Dhaval