My client wants work duration in Maintenance order but dont want Activity cost. If I maintain the activity type of workcenter as zero, costing error status pop up at the time of order release.

If i maintain the activity type 1 paisa, some cost will be introduce to order.

Can there is any way, so that we can have work duration in maintenance order, without getting any cost.

Note: We are confirming using collective order confirmation method & pulling the actual data maintained in Maintenance order while confirming.

Thanks in advance

Santosh

Add comment
10|10000 characters needed characters exceeded

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Apr 22, 2011 at 05:46 AM

    Hi,

    Have you tried by maintaining Zero Price in KP26 against activity & cost center?

    Regards,

    Maheswaran.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      Follow this path & link.

      Plant Maintenance and Customer Service -> Maintenance and Service Orders -> Functions and Setting for Order Types -> Costing Data for Maintenance and Service Orders -> Assign Costing Parameters and Results Analysis Keys

      Remove the costing variant for the order type.

      Actual Cost not displayed on PM Orders

      Regards,

      Maheswaran.

  • Posted on Apr 22, 2011 at 09:00 AM

    Hi Santosh

    If you are using internal control key so you can uncheck option of costing in Control key or you can also make changes in costing variants in which make activity price determination option as Blank (ie no price determination).

    Shail

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      1)By maintaining activity type with base unit year & maintaining activity rate as 0.01 paisa, solved my problem.

      2)Other option of removing cost element assignment to value categories, i think may raise costing error.

      3)Option third also helpful by deactivating cost relevant.