Hi All,
We had imported CCMS jobs from R/3.The CCMS Job consists of 5 steps in it.Job Chain was created for these 5 steps in Redwood after importing the Job.We had configured additional step 6 to raise Operatro message if any of steps from 1-5 fail.
Issue Operator Message is raised but we are not able to restart the failed step(we are able to restart the entire chain again)
Example:
If Job chain failed at step 2 and if reply the operator message to restart step2. New Operator message is again raised and step2 is not restarted in r/3 target system.
Request your help on this.
We are in M28.21-37852