IP19 & IP24

Former Member
0 Kudos

Hi,

Please tell me difference between IP19 & IP24 T codes. What are the different business cases when we need to use IP19 and the same for IP24?

Regards,

Kedar

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

IP24 - This will give you the Orders created as Overview. You cant change or simulate any values here.

IP19 - Both Overview & Simulation available. Here you can fix the plan date for Hold calls in some other dates. You no need to plan separately to postpone or advance the order or one order with subsequent orders.

Try this.

Schedule the Maintenance Plan in IP10. Keep the calls on hold (i.e., dont create the order). Now go to IP19 & select the tabluar & Maintenance Plan simulation option.

In the report, near "Maintenance Item Overview", there is change option "Fix call up", that will enable you to change the "n" no. of orders to change their plan date.

You can release the call object or you can skip the call object.

There are number of options available which we cant do in IP24.

Regards,

Maheswaran.

Former Member
0 Kudos

Hi,

Generally IP19 is used if the Scheduling overview is to be seen in Graphical or Tabular view whereas IP24 is used for getting the Scheduling Overview List. Also IP19 is used for Maint. plan simulation and Gen. object selection is comparatively easier.