Hi,
We are on PPM5.0. We are able to create cProjects Project and replicate to PS upon u201CFlag for transferu201D.
We also have cost/revenue rates, for roles. We have roles assigned to tasks, and intend to transfer the costs (product of cost-rate and role-task-assignment hours) to show up in PS.
We are not using the HR org. The question is regarding the cost element and activity types.
After replicating the Project Type, Cost/revenue rate from cProjects to the accounting system, we link a cost element, activity type to the Cost/Rev rate.
Suppose, we have Cost Element u201CCu201D, and Acticity Type u201CAu201D, linked to the Cost/Revenue rate (the Org. is marked to u201C0u201D). How do we need to link the corresponding u201CCu201D, and u201CAu201D to the WBS elements to be able to see the Planned Costs?
Currently, we get Planned Values as 0, and are not sure whatu2019s more to be done to get the planned costs.
Please advise.
Thanks.