Need New GL with Material Ledger?

We are running ECC6 with the Classic GL and PCA turned on. A request has come in to install the Material Ledger for one of the countries on our SAP Roadmap. It is my understanding that it is required to put in the New GL before the Material Ledger. Is this correct?

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Best Answer
    Posted on Apr 20, 2011 at 04:24 PM

    Dear Tim,

    You can put ML before New GL.

    When NGL was released several companies already had all modules running and even then it was perfectly possible its activation and installation

    Regards

    Add comment
    10|10000 characters needed characters exceeded

    • Dear tim,

      as I said it's OK to to configure the NGL at any time, but I recommend before any module cost controlling, that is The NGL uses cost centers and profit centers.

      When the NGL is activated, it starts to use new objects and data tables for the reconciliation of cost and document split, so that your case does not matter in relation to ML. Cost Control is important.

      Regards