Dear All,

How to ensure that PGI Date/Loading date etc. in delivery flows into Shipment doc.I have assigned copy routine 8 in shipment type.The leg is determined by selecting the connection points in VT01N but when I am clicking on the deliveries button no deliveries are found even though the departure and destination points have been entered.

Can someone please help me regarding this issue.

Regards

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Apr 20, 2011 at 10:34 AM

    1) Ensure that the route is maintained in delivery header

    2) Try by having blank fields under the tab Delivery status in VT01N and input the delivery reference against Outbound delivery

    thanks

    G. Lakshmipathi

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Lakshmipathi Ganesan

      Sir,

      After selecting stages I am doing everything as instructed by you but even then I have to maintain the dates by selecting Mass changes-Actual Deadlines and status and Plan dates.I want the dates to flow from delivery-Processing but it is not happening.

      Please suggest what to do.

      Regards.

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.