CK11N for purchased products

lavanya_latha
Participant
0 Kudos

Hi,

Can somebody please tell me if we can use CK11N (Cost Estimate) for purcahsed products.My client wants to use CK11n for Part type F Components

Thanks,

Lavanya

Accepted Solutions (0)

Answers (5)

Answers (5)

ajaycwa1981
Active Contributor
0 Kudos

Hi

You can run CK11N for purchased products.. However, if the price control is not S, it wont be of any use...

depending on your valuation variant, if the price exists for the material - The cost estimate would go through

br, Ajay M

lavanya_latha
Participant
0 Kudos

Hi Ajay,

Thank you for the response. For our client the purchased parts are always price control V .In that case will we be able to run CK11N for the purchased products. Could you please reply.

Regards,

Lavanya

ajaycwa1981
Active Contributor
0 Kudos

Hi Lavanya

Yes, you can run the cost estimate.. But the Std cost would nt be of any use because your Price Control is V

br, Ajay M

lavanya_latha
Participant
0 Kudos

Hello Ajay,

Could you please explain why the Price Control V is not of any use for cost estimate and but will have effect for Price Control S. Also we are able to run a report which shows the BOM underneath with prices for purchased parts with price control V.

Can you please help me with the answers. Thanks in advance.

Regards,

Lavanya

Former Member
0 Kudos

Hi Lavanya,

The objective of running a std cost estimate is to arrive at a standard price takiing into consideration the actual RM and activity consumptions during a specific period. If you are having price control V(moving average price) , even if you do std cost estimate, mark and release, still your transactions will be happening in Moving average price only. So it does not make any sense to have a price control V and to carry out std cost estimate unless your objective is only to compare the moving average price with std price.

Best Regards

Vimal

ajaycwa1981
Active Contributor
0 Kudos

Hi Lavanya

Std Cost will impact your inventory valuation and COGS only when price control is S

WIth V - It wont play any role except for Information Sake

br, Ajay M

ajaycwa1981
Active Contributor
0 Kudos

Hi Lavanya

Std Cost will impact your inventory valuation and COGS only when price control is S

WIth V - It wont play any role except for Information Sake

br, Ajay M

ajaycwa1981
Active Contributor
0 Kudos

Hi Lavanya

Std Cost will impact your inventory valuation and COGS only when price control is S

WIth V - It wont play any role except for Information Sake

br, Ajay M

ajaycwa1981
Active Contributor
0 Kudos

Hi

You can run CK11N for purchased products.. However, if the price control is not S, it wont be of any use...

depending on your valuation variant, if the price exists for the material - The cost estimate would go through

br, Ajay M

ajaycwa1981
Active Contributor
0 Kudos

Hi

You can run CK11N for purchased products.. However, if the price control is not S, it wont be of any use...

depending on your valuation variant, if the price exists for the material - The cost estimate would go through

br, Ajay M

ajaycwa1981
Active Contributor
0 Kudos

Hi

You can run CK11N for purchased products.. However, if the price control is not S, it wont be of any use...

depending on your valuation variant, if the price exists for the material - The cost estimate would go through

br, Ajay M

Former Member
0 Kudos

Hello,

you can check SAP note 351835

br, Guido