How to get the output of MRP in the following sceneriao:

We are maintaining "Maximum stock level" of ROH type material. After MRP we want the output as OUTPUT = Maximum Stock Level-(Current Stock+Reservation Qty).

To get the above output, what is required to be done?

Thanks,

Sac

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Apr 20, 2011 at 08:54 AM

    Sac,

    After MRP we want the output

    I guess I will assume that you are talking about Procurement Proposals, and not one of the other MRP outputs. Please confirm

    Reservation Qty

    Are you talking about inbound reservations, outbound reservations, or both?

    Maximum Stock level is used to determine the size of the procurement proposal. It has no impact on triggering the creation of a procurement proposal.

    What MRP Type are you using?

    Best Regards,

    DB49

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.