Hello,
my company planned to change the allocation cost element for some activity types at year end. They forgot to do this. As a result they went for period 1-2 with the old combination. On march the created new activity types with new allocation cost elements. Now it is not clear how to post the values (period 1&2) from the old allocation cost element to the new one? Is this generally possible?
Thank you in advance for your help.
Kind Regards
Thank you for the very fast proposal.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
There is no Std way of doing this... You cant transfer the cost from Old cost ele to new one...
The only work around is to
a. Do KB21N from Cost center to Prod order with a -ve Qty for the Old Activity Type
b. Issue the activity from Cost center to Prod order again with +ve Qty & New Activity Type
br, Ajay M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
There is no Std way of doing this... You cant transfer the cost from Old cost ele to new one...
The only work around is to
a. Do KB21N from Cost center to Prod order with a -ve Qty for the Old Activity Type
b. Issue the activity from Cost center to Prod order again with +ve Qty & New Activity Type
br, Ajay M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.