Hi,
We have an issue in commitments records. We raised a 3rd Part Req for Network which was then converted to PO. Now, the Commitments Table COOI is having the PO line items but is not having PR line items in it. Table COSP is having entry with value type 21. So there's an inconsistency in both the table.
Could anyone please advise how this can be resolved.
Best Regards,
Mohammed T Haque
HI,
1. If the PO is a service PO, then based on the SAP release you are in, there are notes available.
2. run "RKANBU01" & cross check.
3. Use the "Closed" indicator in PR & cross check the table entries again.
regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
i think it is a standard behavior. because PR commitment convert into PO commitment once PO has been created.
PR commitments considered as internal commitment and PO commitment is considered as external commitment. Once the PO is created with reference to a PR system converts internal commitment to external commitment.
hope it clears your doubt.
Tnx.
Abdul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.