Labor wise costing

Hi Experts,

I want to do a costing based on the different rates as per their skills, for e.g - for semiskilled 50$, skilled 150$, or can we do costing based on the person ?

could anyone help in this ?

Regards,

Rip

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Apr 19, 2011 at 10:25 AM

    You need to create different acitivity type with the help of Tcode KL01.

    And then you need to assign activity type to cost center and there you can maintain hourly rate.KP26

    And this cost center and activity type you can use in work center.

    Regards,

    Edited by: vaidyas09 on Apr 19, 2011 12:26 PM

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Apr 19, 2011 at 10:22 AM

    Hi

    You cannot do this by a person. To do something like this you need to create several activity types (for instance, each activity type have a 1:1 relationship with a person).

    Regards,

    Rogério Reis

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.