Hi, i have assigned formulas in capacity view of the resource. now created a process order using this resource. now checking the cm01 to check the "requirements". but required capacity shown as zero. please advise what should i check and why requirements were not generated.

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Apr 18, 2011 at 03:42 PM

    check the following

    - in the resource detailed capacity screen "finite scheduling is ticked"

    - In resource scheduling tab capacity you rae looking for is assigned

    - All capcaity and scheduling famulas are maintained.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Apr 18, 2011 at 03:29 PM

    hi...

    Check the attributes of the control key assigned to work centre.

    Check the work sceduling profile assigned to material and the attributes of the worksceduling profile.

    Please revert back in cases of any issues....

    The

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.