Remaining Work not showing Correctly in CN47N

31 Views

Dear Experts,

My case is as following.

1.I Define amount of work 1 M3 in an activity in CJ20N

2.I confirmed 2 M3 of work, and it executed correctly.

3.I changed amount of work to 5 M3.

Remaining work should be 3, But its showing Zero in CN47N

Kindly suggest

Regards