Is "delivery complete" indicator in delivery tab be set after full service receive ( t-code ml81n). Here i found no.

Is it possible to do something so that system automatically set delivery complete" indicator in delivery tab after full service receive.

Kindly help.

Thank you

Best regards,

Zusen

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Apr 18, 2011 at 08:13 AM

    Hi,

    For Material as per the requirement you can maintain the tolerance limit for the PO Line item , once the material is received system will put the Delivery completion indicator.

    For Service's you need to put Final Service Entry Indicator for the Last SES for the PO In ML81N prior to saving the document, these will ensure the delivery complication indicator is set for the PO line item

    regards

    Mascot

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.