Dear Experts,
We need to have purchase requisitions created in MD04 only for the vendor delivery days. I.e) if a vendor delivers only for 3 days in a week then we need to have purchase requisitions created only for the 3 days for the in MD04. please advise...,
Thanks....
Hi,
You can trigger this by using the correct MRP settings (lot size key "PK") in conjunction with a correctly set planning calendar you are able to have the MRP generate purchase requisitions based on the required dates.
Planning calendars can be set in customizing SPRO->Production->Materials requirement planning->Master data->Maintain planning calendar.
Edited by: Peter Pallen on May 5, 2011 10:28 PM Lot size key added