We need to have purchase requisitions created in MD04 only for the vendor delivery days. I.e) if a vendor delivers only for 3 days in a week then we need to have purchase requisitions created only for the 3 days for the in MD04. please advise...,

Thanks....

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Kindly goto MD25 and craete weelday specific planning calender and check days proosed by system and please used Consumption base planning for this purpose

Petepall
Contributor
0 Kudos

Hi,

Consumption based planning is not a requirement for this, you can run it also for normal deterministic planning purposes MRP type PD, P1

Petepall
Contributor
0 Kudos

Hi,

You can trigger this by using the correct MRP settings (lot size key "PK") in conjunction with a correctly set planning calendar you are able to have the MRP generate purchase requisitions based on the required dates.

Planning calendars can be set in customizing SPRO->Production->Materials requirement planning->Master data->Maintain planning calendar.