Carryforwarding of Rem.Order Plan to next fiscal year.

17 Views

Hi

Experts,

I have a requirement of carryforwarding the Remaining order plan to the 2011-12 fiscal year. I am using WBS Element, Network and activities.

Example: I have a plan value of Rs. 1000=00 and Actual value of Rs. 600=00. The remaining order value of Rs. 400=00 is to be carryforwarded to 2011-12 fiscal year. The Budget of Rs. 1000 - 600 = 400 is carryforwarded through CJCO. If I do network scheduling by entering the start date 01.04.2011 and end date 31.03.2012, the entire plan value of Rs. 1000=00 is coming to 2011-12 fiscal year. At this stage the budget is only Rs. 400 and giving error in commitment check. Any help please.

Thanks in advance

Venkat