MICN Planned Count Date

We are having issues with the planned count date in MICN. We have the float & interval set as 4 days in the configuration.

we have posted a physical inventory document on 04/09 and when i try to create a new inventory document for 04/16 in MICN, system is changing the date to 04/18. I am not sure why it is jumping 2 days ahead. Did anyone face similar issue?

Please let me know.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Apr 16, 2011 at 09:29 PM

    Figured it out. Its because of the factory calendar setting.Saturday/Sunday was set as non-working days,so when we put the Saturday as planned count date, system was taking the next working day which is Monday.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.