hi Dear,

is it possible to set activity price calculation method by company or cost center?

seems price calculation method can be set up at planning version only?

my scenario like this:

companies under the same planning version and the same activity type.some company want average method and other companies want period-based method

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • Posted on Apr 14, 2011 at 10:37 AM

    Hi

    Price calculation can be done at Planning Version only.... If your companies have different opinions about costing, then you should have separate contr area

    However, there is a workaround, which can help in Std Costing

    In the Planing Version - Choose Periodic Price.. however, in your Valuation Variant In Costing variant - Choose Strategy "Plan price as average of all Fiscal periods".... This will have avg price for Std Cost Calculation....

    However, during Actual price calculation, it will be periodic only...

    br, Ajay M

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.