Hi,

I have a problem with COMAC running in background. It's replacing order status from MSPT to MANC even though order still has missing parts.

I think material availability is not checked, system should have MANC and MSPT together.

Please advise what can be the reason.

Thanks.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

MANC & MSPT would be mutually exclusive.

A MANC is set when the order has no av. check carried out for it. So check your COMAC job for the reason this order not being part of Av. check run.

I would suggest run Av. check for this order again & then you would see its either MSPT or MACM. If there is some error, then check the error log.