Content Activation - Error Solman 7.2

Dec 13, 2016 at 01:30 PM

814

avatar image
Former Member

Hi Experts,

Facing an error in Content Activation step "Readiness of Non-Production Content" step in Solman 7.2 system. The step fails and it shows that 1 Source Solution has some issue.

Unfortunately, this Solution did not show any error in PREPARE_ACTIVATION but it throws an error here. Due to which the GP does not proceed and the other content is also left out(its a sequential process)

My generic question is:

-Is there any way we can change the PREPARE_ACTIVATION to edit mode at this stage, so we can de-scope that solution at this stage.

- Is there any way we can skip that Solution at this activation stage and proceed with the rest?

Any help would be appreciated.

Thanks,

Shaswat

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

7 Answers

Prakhar Saxena
Dec 15, 2016 at 09:36 AM
1

,

Hi Shaswat,

It is common to get these kind of errors but you can't pass them unless resolve it.

What you should notice is there is one error and other are warnings so you need first focus and remove the error and then you can work on warnings as per this screenshot.content-activation-gp-error.jpg

you may have not maintained it but it may be required as now you are in the stage of merging everything into your solution and this is why it is producing this error.

Please check the content activation guide to work and resolve these conflicts ...normally you can do this in the earlier activities or you can notice what has been assigned for your new logical component group and adjust them as per case. Check the guide.

https://wiki.scn.sap.com/wiki/display/SM/SAP+Solution+Manager+7.2+Content+Activation

this should help you further.

Thanks

Prakhar

Share
10 |10000 characters needed characters left characters exceeded
avatar image
Former Member
Dec 16, 2016 at 07:18 AM
1

Dear Shaswat,

it is still possible to descope at this stage. There are several steps. Details are too much for a short answer here. Due to the complexity and possible pitfalls, open an incident with component SV-SMG-IMP-BIM.

Best regards,

Dr. Franz-Josef Krämer, SAP Development

Share
10 |10000 characters needed characters left characters exceeded
Karthik Paramasivam Mar 30, 2017 at 07:56 PM
1

Shaswat,

Try to create read RFC for listed system and re-execute the steps.

Make sure you have implemented all the latest note from latest content activation guide.

If still error exist, As per your diagram error showing in non-prd branch readiness check job, so just go to SOLADM->system landscape ->go to particular error system Logical component group and assign production system to development branch -> development system and re-execute the non-prd readiness step. it will solve the issue.( because you didn't get any issue on PRD branch readiness check.so assign PRD system to dev system for the time being)

After content activation completion, reassign the development system in maintanance branch.

Rg,

Karthik

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Karthik,

if i have already created the RFC's and existing project can not be founded in the SolMan 7.2 scope?

All Notes we have already implemented

Rg,

Abzal

0
Prakhar Saxena
Dec 14, 2016 at 01:54 PM
0

Hi Shaswat,

Could you expand the link which shows the error in details where you have the job failed for non production system.

Please share the screenshot

Thanks

Prakhar

Share
10 |10000 characters needed characters left characters exceeded
avatar image
Former Member Dec 15, 2016 at 05:19 AM
0

Sure Prakhar, here it is :

(may need to maximize to see it fully)

Guided Procedure Log -

content-activation-gp-error.jpg

It stops at the 2nd source solution (out of 10) , and we would like to proceed with the rest.

The error shown in SLG1 and GP Log is that a particular LCG does not have RFCs for Role Type "E" (Training System).

We had not maintained any systems for the corresponding logical component in 7.1, it was an empty LC like many others.

At the same time, we did not get any warning regarding this is Guided Procedure "Prepare Activation"

Thanks for your help!

Regards,

Shaswat


Share
10 |10000 characters needed characters left characters exceeded
avatar image
Former Member Dec 22, 2016 at 04:09 AM
0

Hi Franz,

Thanks for your reply.

This is an issue as we can't descope, and there is no clear guideline how to resolve the issue.

It is any empty LC, like many others. We have created RFCs now, still the issue doesn't go away.

We have raised an OSS : 467057/ 2016 , please help us to resolve it.

Thanks a lot !

Regards,

Shaswat

Share
10 |10000 characters needed characters left characters exceeded
avatar image
Former Member Mar 30, 2017 at 11:16 AM
0

Hi Shaswat,

Implement the note 2449951 retry again

Thanks
Sreekantha