SNP subcontracting with co-products

51 Views

Dear experts,

We are trying to implement an SNP scenario with subcontracting, and our PPM contains co-products.

The heuristic creates a stock transfer from a subcontractor to a plant and a planned order on the subcontractor.

That is according to the documentation. The planned order contains both an output node for the main product and another output node for the co-product. We are missing however a stock transfer for the co-product from the subcontractor to the plant. Does anyone know whether it is a limitaion of SAP standard or something is not yet properly configured? I would also appreciate any ideas on how to solve the issue through custom developments.

Best regards