on 04-08-2011 9:18 AM
Dear All,
I had created a sales order for 10 MT of Steel where the VPRS condition type picked up 50 INR whcih is the standard price in the material master.When I tried to do PGI after 15 days the Standard price was updated to 75 INR through /MR21.But the material document price is still showing as 50.
How to resolve it.
Regards.
Hi bob,
VPRS in the order always shows avg.moving price from material master at the time you inserted the item.
At the time of billing it will for sure not take the VPRS from the order but the actual one from material master or cost price (MIGO on purchase order) when you had to purchase the item.
Hope this helps
Wolfi.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.