we need reciepient wise budget control for maintenance orders

Hi,

whlie creating maintenance orders in components tab we have field "reciepient". we need Reciepient wise budget control for maintenance orders.

for example: if we assign for reciepient "dip" budget 1000 , if for that reciepient exceeds the maintence cost then system not allow to create maintenance orders

Regards

ganesh

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Apr 08, 2011 at 04:48 AM

    Hi

    Kindly check with abaper whether it is possible with some user exit, since the recipient is freely defined text which will not have better control .

    check with standard budget control either order or order group or through wBS element etc

    regards

    thyagarajan