on 12-13-2016 10:52 AM
Hi All,
in 0co_pc_01 i am not getting input material and KF''s related to it like Variable cost and quantites, and also actual/plans data seems to be swaped...any inputs on same?
Regards
Ashu
Same has been Solved after maintaining Recipe of Finished goods (CS01) tcode.
and component Material Master has to be maintained with Following Setting.
MM03 > Material Number> Costing1 Tab> Material Origin Check Box Tick.