Hi All,
I have a scenario that from a particular date a wage type should be calculated from a different %. (10% of Base wage type) Unfortunately I dont have much knowledge on the PCRs, but I have found out that in the currentl system, there is a PCR which calculates wage type calculation on % from a particular date.
what i have done is just copied that one and changed the date with new % and inserted into the schema. But now when I check for the new period, it is cumulating both old and new amounts. I want only the current one which i have inserted.
How do we make system take into account only the new % and not old?
Please advise.
Regards
Rajguru
Hi Rajguru,
Have you commented the Old PCR line in the schema with *.
Regards
Venu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If it is for a Payroll PCR, use operation CMPER as the first decision in your PCR, as in CMPER1101 (compare with pay 01 of 2011).
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.