Hi All,

I have a scenario that from a particular date a wage type should be calculated from a different %. (10% of Base wage type) Unfortunately I dont have much knowledge on the PCRs, but I have found out that in the currentl system, there is a PCR which calculates wage type calculation on % from a particular date.

what i have done is just copied that one and changed the date with new % and inserted into the schema. But now when I check for the new period, it is cumulating both old and new amounts. I want only the current one which i have inserted.

How do we make system take into account only the new % and not old?

Please advise.

Regards

Rajguru

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Rajguru,

Have you commented the Old PCR line in the schema with *.

Regards

Venu

former_member193210
Active Contributor
0 Kudos

If it is for a Payroll PCR, use operation CMPER as the first decision in your PCR, as in CMPER1101 (compare with pay 01 of 2011).