Hi every body,

i have a requirement in Production module. where 'M1' is the main item for which S1, S2 and S3 are the sub items.

In that for S3 there is a BOM C1,C2 and C3 are the component items. The requirement is S3 is a salable item not a phantom item.

Client will manufacture S3 in bulk quantities and keeps in the inventory. whenever there is a requirement for main item M1, they use these items S1,S2 and S3.

when they are raising a production order for the M1,there should not be item S3 in the issue for production as it is already there in lump sum

quantity.

For this which BOM type has to be used and which production order type has to be used...