Apr 06, 2011 at 05:50 AM

OPK4 Process Order Confirmation parameter

400 Views

Dear All,

In process order confirmation i want do a configuration like

Operation 10

Phase 20 0010(supr.ope)

Phase 30 0010(supr.ope)

Operation 40

Phase 50 0040(supr.ope)

now I maintained a relationship between 50 & 30 like "30 is predecessor of 50"

I required during confirmation if confirmed quantity of phase 30 is 50 and now if I go for phase 50 confirmation system should not allowed confirmed quantity >50 of previous confirmed operation 30

for that i have done setting in OPK4 like

Checks

Operation sequence " E Error when operation sequence is not adhere to"

but system is allowed to do a confirmation more than 50 qty of operation 30

so what is the meaning of operation sequence check in PPPI

Regards,

Murari Shah