on 04-05-2011 5:20 PM
Dear Experts ,
I need some help with SNP Optimization execution ...... Actually i am executing discrete optimization , using weekly buckets.
For i.e
I have a demand with 100 pc ..... minimum lot size is 60 and max lot size is 62 .....
SNP should create two lots with 60 pc each one , but it is creating one lot with 60 and a second lot with 40 ..... It is considering last lot exact to fulfill demand .....
All PDS have discretization flag and the relevant parameters for discretization are set on OPT profile .....
I some setting missing ?
Please i need some help asap .....
Kind Regards
Mauricio
Hi,
What is the discretization horizon you have maintained.
Thanks,
nandha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.