Dear Gurus,

can be set Month,week in one screen because initial screen only option we can choose either M or D.

iva

S

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member189817
Active Contributor
0 Kudos

Hello Siva,

What Mr Sunderesan sugessted is nice solution.This is the only way to enter requirments for Month and week in MD61.

Regards,

Velmurugan S

sundaresan_velayudam
Active Contributor
0 Kudos

in MD61

give any period material and plant

and go to schedule line

and enter period indicator , requirement date and quantity

In period, you can maintain month or week.

so that you can maintain month and week plan

In one screen

Note: system will take both plan during MRP

If you want to enter month and split to weekly, then use split in order to split to week

former_member212685
Participant
0 Kudos

Dear

i know this if we have any customized setting please let me know.

siva

sundaresan_velayudam
Active Contributor
0 Kudos

Dear,

we don't have any customizing setting for entering Plan for weekly and monthly in single entry.

at a time we can give only one period

former_member212685
Participant
0 Kudos

thanx