Hi,
I want to inspect the first character of a material once in 10 lots during goods receipt inspection. If the first character is OK for the first lot then remaining 9 lots should be skipped otherwise I have to inspect the 2nd lot for the same. For which I have defined the Dynamic Modification Rule (DMR) as follows:
In inspection plan header I have mentioned the DMR level as DMR at Char level
Dynamic Modification at the Usage Decision
I have mentioned the reset period in days as 9999
Stage -
InspSev----
-Skip
IST -
SHORTXT -
STC
NO.OF INSP
MAX -
1--
2--
I have implemented the above DMR rule. I have recorded results for the first lot due to DMR I found more than 10 lots are skipped for the particular characteristic.
Please help to solve this issue.