We have a centralised subcontracting contract (item category "L") in place for a material. The requirement is to create a scheduling agreement with reference to this contract line item item category "Blank" (Standard).

But the item category field is greyed out (display only) when we try to create scheduling agreement with refernce to contract on the "Adopt + Details" screen. And we are not able to change the item category "L" to "Blank". Is there a way we can make this item category field editable on this screen before we hit "Adopt + Details".

I have tried most of the field selection configuration, but there is no specific field selection group for this screen.

Please note that the system allows you to change the item category when you create a PO with reference to this contract.

Accepted Solutions (1)

Accepted Solutions (1)

former_member182489
Active Contributor
0 Kudos

The Process you trying to do is wrong . IF the Contarct have a valid L , then all Scheduling agreement/PO w.r.t that Contact should come with L .

You can check with the User the eexact requirement and manage a new process for their requirenent.

Former Member
0 Kudos

Thanks Manu for your suggestion!

But this is the process that we need to map. Request others to respond if they have comes across such a requirement and able to address it.

Again I want to make a note here that if it is possible on POs, there should be a way to make it work for SAs.