While transferring resource, getting the error message below;

Field SNPLC is not an entry field for resource type 02

Message no. /SAPAPO/DMRES149

Is that something to do with CFC9??

Please help.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

You have defined the resource type as 2 ( single activity resource) which is PPDS relevant but in the Planning parameters tab of the APO resource you have defined it as SNP relevant.( Not ticked the Not SNP relevant)

Request you to make tick in the Not SNP relevant field and then try Ciffing.

Since SYSFAIL has happend request you to clear the failed Queues and then CIF it.