on 03-31-2011 7:59 PM
Hi
Is there a configuration or a standard way to update only the actual start date of the activity at the moment of partially confirm?
Currently I get an error message "RU274 please enter either actual start and actual finish or none of the fields"
.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks, just confirmed there is no work around
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
As far as I am aware, system will not allow. There is no configuration that can help you achieve the aim of entering only actual start date.
BR
Anjali.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Do you think there a posibility to workaround this with any of the confirmation users exits or no posibility to "trick" the source code?
CONFPS01 PS confirmation: Determine customer specific default values
CONFPS02 PS confirmation: Customer specific input checks 1
CONFPS03 PS confirmation: Customer specific check after op. selection
CONFPS04 PS confirmation: Customer specific input checks 2
CONFPS05 PS confirmation: Customer specific enhancements when saving
thanks