Employee hours transfer from one project network to another project network

Dec 13, 2016 at 07:55 AM

108

avatar image

Hi Experts.

One of my client by mistake booked employee hours to one project network in June-2016, now they want to transfer those employee hours to another project network. is it possible in standard SAP.

Through CAT2 tcode they have booked June 2016 employee hours to new project network. but those hours are not charged to network activity in CJI3 report.

I need your valuable suggestions...

Thanks,

Kishore

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Ratnakar Venkat Dec 15, 2016 at 12:06 AM
0

Hi Krishna,

Couple of options are available.

1.You can change this in CAT2 ,- ve hours with old project NWA and +ve hours with new project and transfer hours to project.

or

2.KB21N -repost manually -this is a two step process.

- ve hours with old project NWA

+ve hours with new project NWA

you may need a CO consultant help for this entry.

Thanks,

Rau

Share
10 |10000 characters needed characters left characters exceeded
Ken Melching
Dec 18, 2016 at 08:24 PM
0

Hours booked in CATS do not show posted on the network until you perform CATS Transfer, and since you are correcting hours from the past you have to set te posting date to an open period.

Share