Hi Experts.

One of my client by mistake booked employee hours to one project network in June-2016, now they want to transfer those employee hours to another project network. is it possible in standard SAP.

Through CAT2 tcode they have booked June 2016 employee hours to new project network. but those hours are not charged to network activity in CJI3 report.

I need your valuable suggestions...

Thanks,

Kishore

Accepted Solutions (0)

Answers (2)

Answers (2)

kenmelching
Active Contributor
0 Kudos

Hours booked in CATS do not show posted on the network until you perform CATS Transfer, and since you are correcting hours from the past you have to set te posting date to an open period.

Former Member
0 Kudos

Hi Krishna,

Couple of options are available.

1.You can change this in CAT2 ,- ve hours with old project NWA and +ve hours with new project and transfer hours to project.

or

2.KB21N -repost manually -this is a two step process.

- ve hours with old project NWA

+ve hours with new project NWA

you may need a CO consultant help for this entry.

Thanks,

Rau