Dear All,

I am using strategy 50 for a material. It has two versions V1 and V2. I have maintain Quotta Arrangement 60, 40 % for V1 and V2 respectively. Also entered PIR of 1000 TO. and sales order of 500 TO in same month. When i run MRP system creates two plan order for PIR as 60, 40 percent for V1 and V2 but against sale order it creates only one plan order with V2.

i think it should also create two plan order having 60, 40 ratio of V1 and V2 as in case of PIR.

Infact it worked for PIR but not for sale order.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Please check the below thread.

[;