Not getting detail of Assigned value

Dear Experts ,

I am not getting detail of Assigned value in S_ALR_87013542 & S_ALR_87013558.

I have no commitment but its showing actual cost is 57.Kindly put some light on in.

Regards

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Mar 31, 2011 at 10:20 AM

    Hi,

    in tcode cj31; Extras -> Availability Control -> Analysis, you will get the assigned value full details.

    Regards,

    Harsh.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hiiii

      Project Hierarchy Reports work well with configurations of value categories in customizing

      Check for the creation of value categories in configuration using the transaction code OPI1 and check for consistency using the t.code CJVC.

      Hope this helps....

      Regards

      Kaashif M

  • avatar image
    Former Member
    Mar 31, 2011 at 10:20 AM

    Assigned value is calculated from your "Commitment" & "Actual" values postings. You will not get any details in those reports. See the line items of your Commitments & Actuals individually.

    You can analyze the contributors to your assigned value (line items with value types) in CJ31, availability control analysis.

    regards