Working Hours and Overbudgeting Issue

29 Views

Dear All,

I am using CMP2 transaction for Workforce Planning. For example for one project I have created 2 activies (A and B) under one Network. And for these activities I have planned 20 and 30 hours respectively. Now when I am assigning employees from CMP2 transaction under this network activities, I am able to allocate more working hours than what is actually planned.

For example for Network Activity A I have fixed 20 hours. But from CMP2 transaction I can allocate more than 20 hours to employees. While doing this there is not standard error or warning appearing so Project Managers are allocating more hours to employees. Because of this, project is getting OVER BUDGETED.

How to fix this issue? This is the standard functionality that SAP has provided or this is some configuration Issue? Can you help me to solve this.

Thanks in advance,

Roshan