Dear Experts,

I am having an issue with respect to availability check .

I am using combined planning strategies 70 and 40 . For component planning i am using 70 and for finished material i am using

planning strategy-40. For Finished material in-house production time is 1 day. Now when the sales people are creating sales

order, when they perform the availability check the system is showing available in the next date for irrespective of quantities.

Ex: if they create sales order for 1000 numbers also it showing one day and even for 10,000 also it is showing one day.

I have done all the necessary cusomization for availabilty check. is there any way of settings like if stock is there the system

should check only in-house production time and if stock is not there the system should check Replinishment lead time(RLT).

Please let me on what basis system is showing this available date for sales order.