当生产订单物料需求后,甚至某些材料已经发料。
这时BOM发生了修改,如何及时的更新生产订单里面的物料需求。
如果没有发料(计划内),可以对生产订单重读PP主数据,但是需要一个一个订单的来读。
如果发料了(计划内),就不能重读。
请教大家怎么更新才好?
需要使用ECN+OCM去处理,参照一下http://help.sap.com/saphelp_erp60_sp/helpdata/en/a5/63198843a211d189410000e829fbbd/frameset.htm
Best Regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
用OCM可以解决这方面的问题。