Hi Experts,

I am using the CN25 transaction for the confirmation of the network activity for the calculation of the actual cost of man hours. In order to calculate the actual cost for an hour rate we had written a one program to pick the hour rate from the HR table..

My requriment, in the CN25 transaction there is no opition to enter the Actual start & end time fields, But in the screen i can see the opition to enter actual date, not for time.

Kindly suggest me how to add the fields to enter the actual start & End time.

Thanks & Regards

Raman T S

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Check the customer specific enhancements for confirmation, for example "CONFPS01 (EXIT_SAPLCORF_006)" whether this can solve the purpose.

OR You may need to make a ZCN25.

regards

Former Member
0 Kudos

Hi Krisap,

Thank you for your reply.

I want to create the user exit in order to add fields in the CN25 transaction. How to create the ZCN25 transaction code.

If u see in the customization under the Project system -> confirmation -> define field selection or OPUD tcode. We can see the fields of the start time & End time.

Can any body tell me where this fields are affected when make this fields as manditory.

Thanks & Regards

Raman T S