cancel
Showing results for 
Search instead for 
Did you mean: 

MRP Questions

Former Member
0 Kudos

1) A specific SKU (Material number) is used by 2 different parts of the business (it is sold as a spare part and it is used to repair units in house). Hence, this part has primary and secondary requirements (Independent & dependent demand). The inventory is kept separate in 2 different bins/locations. The challenge is to plan the replenishment of this material in MRP. MRP will look at the combined requirements and generate one Purchase Requisition that in turn is converted to a Purchase Order, which then is received (in bound). The problem is that if we want to keep them separate in storage we need to somehow separate the inventory. Is there a way to get MRP to plan this material separately depending on the source of the requirement? I would not want to create a separate Plant to do this.

2) The other question is as follows:

I have 3 plants, I have inventory for a given SKU at each of the plants. The forecast however is at a u201CPlanning Plantu201D (4th plant) at an aggregated level for all 3 plants and I want to carry out a MRP calculation at the planning plant to determine how much I need to buy (purchase Requisition) for all 3 plants combined.

I would really appreciate your input on this.

Thank you.

Regards,

Sai Mukkamala

832-515-4280

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

For your first question, can you carry out Storage Location level MRP?

For example, The independent requirements (Spare Sale) generated through Sale Order will be triggered at Finished Goods Store. For Dependent Requirement, the requirement will be triggered at General Store.

Regards,

Prashant

Answers (1)

Answers (1)

Former Member
0 Kudos

Assumed answered