Budget check while creating PR using Account assignment cat.A

Former Member
0 Kudos

Hi all,

Following is my scenario:

I had created an asset , in that asset I had assigned WBS in origin tab. My question is when I am making PR using account assignment category A my budget should check, because I had assign WBS in that asset.

Is there any required config to be done.

Regards,

Gagan

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Consult with MM consultant to create a new Account Assignment Category in which

Consumption posting will be asset.

Acct. assignment will be multiple, and

in Fields Asset and Project will be mandatory.

After this when you will create PR using newly created category, WBSE field and Asset field both will be there and budget check will happen against WBSE.

Regards,

Harsh.