Budget check while creating PR using Account assignment cat.A

Hi all,

Following is my scenario:

I had created an asset , in that asset I had assigned WBS in origin tab. My question is when I am making PR using account assignment category A my budget should check, because I had assign WBS in that asset.

Is there any required config to be done.

Regards,

Gagan

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Mar 31, 2011 at 07:28 AM

    Hi,

    Consult with MM consultant to create a new Account Assignment Category in which

    Consumption posting will be asset.

    Acct. assignment will be multiple, and

    in Fields Asset and Project will be mandatory.

    After this when you will create PR using newly created category, WBSE field and Asset field both will be there and budget check will happen against WBSE.

    Regards,

    Harsh.