Needs Solutions

former_member823821
Participant
0 Kudos

Dear All

I am creating a sales Order of a Material having MRP type PD i.e that will trigger to purchase requisition and STOin the supplying plant and afterwards GR is being done.Then you can make PGI and Billing.

The problem is that at the schedule line.the delivery date is 29 th of march as per the inhouse production time maintained in material master[MRP2 views],but user needs it to happen on 28 of march only.

I have changed the inhouse production time to 0 also in MRP2 views of Material Master but still got the same result

Can you plz help me out that is their any other checks for availability ?

Many Thanks

Rakesh Naveen

Accepted Solutions (1)

Accepted Solutions (1)

former_member823821
Participant
0 Kudos

Hi Arun

Thanks for your input

There is no question of Stock availability over here rather it is a make to order through Procument as Stock Transfer from other Plants.

Thats why I am saying that If I put inhouse time 0 then at schedule line it should reflect the delivery date as 28th of march.

ajitsingh6
Active Contributor
0 Kudos

Dear ,

Also check Planned Delivery TIime and make it as Zero.

Regards,

Ajit K Singh

former_member467138
Active Contributor
0 Kudos

>

> Hi Arun

>

> Thanks for your input

>

> There is no question of Stock availability over here rather it is a make to order through Procument as Stock Transfer from other Plants.

> Thats why I am saying that If I put inhouse time 0 then at schedule line it should reflect the delivery date as 28th of march.

Hi,

As per SAP if ur having stock on 28 march then only u can change manualy delevry date as 28 march.

Arun

former_member823821
Participant
0 Kudos

Hi Arun

Thanks for your Concern

I am just making it clear that there is no concern of stock availability rather we are just procuring from other plant.If I put Inhouse production time0,then why it is reflecting 29th of marchI have given all inputs in my trailing mail

How the system is making the margin of 1 days?

Can you plz suggest me on that?

Former Member
0 Kudos

Hi there:

Please go to va03 and double click the item line, then go to shipping tab, record the route, then go to spro, path:Logistics execution/shipping/basic shiping functions/routes/define routes/define routes and stages, then position your route in it, probably you will find transit duration or transit lead time is 1, it means 1 day, it will explain your case, hope it helps.

former_member823821
Participant
0 Kudos

Hi

Thanks for your Input

Unloading Point

Department

Plant 3237 F

Shipping Point DEX1 D

Route

Mat.freight grp

MnsOfTrns type

MeansTransp.

There is no route defined over here.Here the delivery scheduking will be done through procurement only.

Plz guide me where is the setting that pertains to the transit time 1 day.

Many Thanks

Rakesh Naveen

former_member823821
Participant
0 Kudos

Resolved

Lakshmipathi
Active Contributor
0 Kudos

Please have the courtesy to update the forum as to how your issue is resolved; else you can just click the Answered button without adding such unwanted comments.

thanks

G. Lakshmipathi

Answers (3)

Answers (3)

Former Member
0 Kudos

Could you go to MRP3 of material master data, and tell me what's the value of tot.repl.lead time? if it is 1 day, your case made sense.

former_member823821
Participant
0 Kudos

MRP2

In-house production 0 days Planned Deliv. Time 0 days

GR Processing Time 0 days Planning calendar

SchedMargin key 000

MRP3:

Tot. repl. lead time 0 days

Still the seytem showing the delivery date at schedule line is 29th of march.

former_member823821
Participant
0 Kudos

Plz resolve it.

former_member823821
Participant
0 Kudos

Hi Arun

Thanks for your input

Still we are facing the same condition as the delivery date is 29th of narch and even i have reated sales order today itself.ste

Can you plz suggest me that there is some control either at Master data level or config?

former_member467138
Active Contributor
0 Kudos

Hi,

It is master level control only... No configuration.... If u have stock then change manualy in shcedule lines.

Arun

former_member467138
Active Contributor
0 Kudos

>

> Dear All

> I am creating a sales Order of a Material having MRP type PD i.e that will trigger to purchase requisition and STOin the supplying plant and afterwards GR is being done.Then you can make PGI and Billing.

> The problem is that at the schedule line.the delivery date is 29 th of march as per the inhouse production time maintained in material master[MRP2 views],but user needs it to happen on 28 of march only.

>

> I have changed the inhouse production time to 0 also in MRP2 views of Material Master but still got the same result

>

> Can you plz help me out that is their any other checks for availability ?

>

> Many Thanks

> Rakesh Naveen

Hi,

What is the sales order creation date? If it 28 march and inhouse production time is 0 then it should be 28 march only... Just delete and readd item once again ...

Arun