Sales order with Material Delivered through pipeline

Hello Community,

I'm looking for a SAP scenario/solution that can manage Sales order delivered through pipeline.

I found a lot of information about Pipeline but from MM side not SD one.

I also check Oil and Chemmical solution but did not found proper solution

Here is my business case.

1° Sales order is created with 1 month delivery period through Pipeline.

2° System has not to book the entire quantity the fisrt day of delivery but has to book it day by day (can be done through APO)

3° About GI actual delivered quantity is measured and one GI is done at the end of the period.

4° Creation of one Billing for the period.

I proposed a sollution with a POD but Customer want to make GI at the end of the delivery.

If anybody faces this kind of Scenarion help would be apprciated.

Thank you for support

and best regards.

Benoî

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Apr 23, 2011 at 02:48 PM

    Hello,

    We finally decided to create automatically daily delivery schedule in STO and ask to logistic people to create daily OBD and GI.

    Quiet basic and it works.

    Thank you and regards.